Erdos CTL (sometimes also referred as Shenhua CTL) is a coal liquefaction plant at Ejin Horo Banner in Inner Mongolia, China. It is the biggest coal-to-liquids complex outside South Africa with a capacity of 20,000 barrels per day (3,200 m3/d).[1]

The plant cost USD 2 billion, and is owned by Shenhua Coal Liquefaction, a subsidiary of Shenhua Group. It uses direct coal liquefaction technology in a developed by Shenhua Group.[2][3][4] In the first phase, three production lines were installed.[5] The coal liquefaction reactor was manufactured by China First Heavy Industries.[6] Dedicated steel belt cooling systems for a coal slurry solidification were supplied by Sandvik Process Systems.[7] [8]

Construction of the plant started in 2004 and it was commissioned in 2008.[1][9] Trial operation started in mid-2009.[10] Since November 2010, it is fully operational.[11] It uses 10,000 tonnes of coal per day, and can produce 3,000 tonnes of oil. Annual output capacity is 1 million tonnes, comprising 0.62 million tonnes of diesel, 0.32 million tonnes of naphtha, and 0.07 million tonnes of liquefied petroleum gas. For each tonne of product, it uses 7-12 tonnes of fresh water, and outputs 4.8 tonnes of waste water and 9 tonnes of CO2.[4]

See also

[edit]

References

[edit]
  1. 1 2 "China readying giant CTL plant". Upstream Online. NHST Media Group. 2008-06-04. Retrieved 2009-08-02.
  2. "Shenhua signs two CTL deals". Upstream Online. NHST Media Group. 2006-06-12. Retrieved 2009-08-02.
  3. "China's Shenhua plans seven CTL conversion centers". Platts. 2009-06-30. Retrieved 2009-08-02.
  4. 1 2 "Nuclear Process Heat for Industry - World Nuclear Association". world-nuclear.org.
  5. "World's first coal-to-oil mass converter due to start operation this year". People's Daily. Xinhua. 2007-06-22. Retrieved 2009-08-02.
  6. "Shenhua Group begins to install coal-to-liquid devices". People's Daily. 2006-06-17. Retrieved 2009-08-02.
  7. "Sandvik Supplies Cooling Systems for Coal Liquefaction". Mining Engineering. Downstream Today. 2008-01-11. Retrieved 2009-08-02.
  8. "Water Needs Curtail China's Coal Gasification for Fuel yet Conversion to Chemicals Pushes Ahead". Circle of Blue. 2011-04-27. Retrieved 2014-02-10.
  9. "China to Spend $13B on Liquefied Coal Base". Downstream Today. Xinhua. 2007-03-09. Retrieved 2009-08-02.
  10. "Shenhua's coal-to-oil project to start trial operation in July". China Daily. Xinhua. 2009-06-12. Retrieved 2009-08-02.
  11. Bai, Jim; Chen Aizhu (2011-09-08). "China Shenhua coal-to-liquids project profitable -exec". Reuters. Archived from the original on March 6, 2016. Retrieved 2012-03-10.