Edge Rewrite
// HTMLRewriter · presentation

This page was redesigned at the edge.

Cloudflare fetched the original article and streamed it through HTMLRewriter to apply an entirely new visual system without rebuilding the source page.

// request.cf · coarse context

A page that knows where it met you.

Only coarse request metadata is shown. This demo does not display or persist visitor IP addresses.

Country
US
Cloudflare location
CMH
Connection
HTTP/2
Language
Not provided

Ray ID: a23ff6075d7db6ed

Jump to content

Talk:Product-based planning

Page contents not supported in other languages.
Add topic
From Wikipedia, the free encyclopedia
Latest comment: 1 year ago by Benjwy in topic Example Provided Misleading?

Comments by Fred Thwaites

[edit]

Unless I'm mistaken PRINCE2 does not mandate this technique, only recommend it. To this extent it is covered in both the training and certification exam.

FredThwaites 00:07, 23 February 2007 (UTC)Reply

I would hesitate to say that you are correct in your statement Fred, in the book "Prince2 a practical handbook" by Colin Bentley [ISBN 0-7506-5330-2], he states on pg.110 in relation to PL2 Defining and Analysing products; "This is a key point in PRINCE2. If you are not using this step, then you are not really using PRINCE2. It is an ideal method of involving users, specialists and Project Assurance roles in the creation of a plan, without the normal probelms of "design by committe".

So it is my opinion (backed by Mr. Bentley) that Product based planning is critical to the use of this method, and is not merely a recommendation, as the whole methodology is Product based as oppose to the traditional (lower level) activity based planning.

A.N.Other : Project Manager [13:49 29 Feb 2007]

Example Provided Misleading?

[edit]

The text of the article says,

In this sense the product breakdown structure is a great deal more than simply an exploded view of the final end-product.

It then goes on to give an example PBS of that is precisely an exploded view of the end product.

There are probably better examples that could be provided for a PBS, but this is ignoring another potential issue; the example section gives an example of a (poor) PBS, not an example of product based planning.

An example of PBS -> PFD -> activity breakdown -> sequence and estimate may be more appropriate here. Benjwy (talk) 11:05, 17 January 2025 (UTC)Reply